Answer: should be protected due to the fact that their account is insured by FDIC.
Explanation:
From the question, we are informed that after Xavier and Alyssa deposited nearly $55,000 in a savings account at Bigbux Bank, the bank failed and filed for bankruptcy but that the Bigbux was an FDIC member bank.
Based on the above scenario, Xavier and Alyssa should be protected due to the fact that their account is insured by FDIC. Since the bank is insured, their money is safe.
Answer:
FV= $46,031.45
Explanation:
Giving the following information:
Monthly deposit= $450
Number of months= 59
Interest rate= 0.21/12= 0.0175
To calculate the final value, we need to use the following formula:
FV= {A*[(1+i)^n-1]}/i
A= monthly deposit
FV= {450*[(1.0175^59) - 1]} / 0.0175 + 450
FV= $46,031.45
Answer:
d. Rise in price of alcohol
Explanation:
Change in Quantity demanded occurs due to change in Price. Change in Demand happens due to factors other than price - Income, Substitute & Complementary good's price, Taste.
Change in alcohol demand - due to substitute Cigarette price change , Change [Decrease] in alcohol demand - due to change in taste based on anti drinking sentiments, higher risk of alcohol liver cirrhosis , Change [Increase] in alcohol demand - due to change [rise] in Income : These all are due to factors other than price & hence are 'Change in Demand'
Rise in price of Alcohol leads to 'Change [Expansion] in Quantity Demanded' due to price change [rise] .
Answer:
a) a monetary unit for measuring and comparing the relative values of goods.
Explanation:
In the case when the economist said that money could be treated as the store of value so this means that it represent one of the functions of money which can be stored and retrieve later onwards
Also it is a monetary unit that could be used for measuring and also compared the goods value
Therefore the option a is correct
Answer:
It's c.
Explanation:
Program Evaluation and Review Technique (PERT) is a method used in program management. It analyzes the time required to complete each task in a project and so tries to determine the minimum time to complete a project. It was developed by the US Navy in 1957.
In PERT analysis:
- there are 3 time estimates for every activity: optimistic, pessimistic, and most likely
-
you have to find the Critical Path. The Critical Path is the longest path of scheduled activities that must be met in order to execute a project. It is important to know because any problems on the critical path can prevent a project from moving forward and be delayed. Therefore only critical activities can contribute to the project variance.