1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
aliina [53]
3 years ago
10

if 4 bags and 6 cubes are on one side of the scale and 22 cubes are on the other side, how many cubes must be in each bag to mai

ntain balance
Mathematics
1 answer:
Makovka662 [10]3 years ago
8 0

Answer:

4 cubes

Step-by-step explanation:

We can remove 6 cubes on each side and still make them balance. And we got 4 bags = 16 cubes, them we divide by 4 on each side, we can get 4 cube is in each bag.

You might be interested in
Evaluate best answer for brainliest
Nadya [2.5K]
4/5 is the answer unless you need it in decimal

5 0
3 years ago
Read 2 more answers
Please no links because they dont work :).
mr_godi [17]

Answer:

semoga jawapan ini dapat membantu

6 0
3 years ago
Can u all help me????
ira [324]

Answer:

No it doesn't because y has two 3's

Step-by-step explanation:

7 0
3 years ago
Can someone help me solve this and put this on a graph. Just one problem may help.
Sauron [17]
I thought of it as answering a regular equation and imagine it's equal signs but when your done solving you with have like ex x<5 and where ever the butt of the arrow is pointing is where the lines goes if there's ano equal sign below it then it is includive
3 0
4 years ago
mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days
4vir4ik [10]

Answer:

<em>Most likely time, </em>according to PERT (Program evaluation and review technique).

Step-by-step explanation:

PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.

Inside PERT, there are different defined times to accomplished an activity in a project, that is:

  • An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
  • A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
  • A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
  • An <em>expected time</em>, an statistical estimation.

Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":

  • "[...] in as few as 15 days"  is the <em>optimistic time</em>.
  • "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
  • "[...] but most likely will require 20 days" is the <em>most likely time</em>.

As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.

3 0
3 years ago
Other questions:
  • PLZ HELP ASAP CIRCLES
    7·1 answer
  • 2) Where does the red egg belong?
    14·1 answer
  • How do you divide 8 by 10
    8·2 answers
  • 760 hundreds using place-value chart
    7·1 answer
  • Please Answer !!!!
    10·2 answers
  • Find the length of the arc. Use 3.14 for value of tt
    7·1 answer
  • A company makes 120 bags.
    9·1 answer
  • Juanita borrowed $600 to purchase a new computer. She was charged 7% interest for two years. She used the simple interest formul
    11·1 answer
  • −6+3x=9 can some one help me plez
    13·1 answer
  • D
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!