Answer:
assuming that this month was extraordinarily long, and had more days than any other month in history, you worked a total of 5 x 40 = 200 hours
Also, due to length of the month, you will earn 200 hours x $13 = $2,600
Generally months tend to have between 20-23 labor days
Answer:
Option C Internal Control Information
Explanation:
The reason is that variance analysis is the process through which we emphasize control over costs which is solely management accounting and is not linked to financial reporting so the option B is incorrect. This information is internally generated which means saying that the information is obtained from external sources is totally incorrect. The option a is generally correct because this information is part of internal information. But Option C is more relateable here so the better option is Option C.
Question Completion:
What is a price floor?
Answer:
A price floor of $2 for milk producers across Arizona and nationwide means that the government does not want the price of milk to fall below $2. This measure enables dairies to remain in operation. It favors producers to the detriment of consumers, at least in the short-run.
Explanation:
However, assuming that the market was efficient before the price floor was introduced by the government, the price floor of $2 per gallon for milk could cause a deadweight loss to occur. In Economics, a deadweight loss reduces economic efficiency. It implies that consumers pay a higher price for the same quantity of goods they were purchasing before the price floor was introduced. Thus, the reaction of consumers would be to reduce their demand or drop out of the market entirely (instead of producers dropping out of the market through the normal operation of the market forces).
Answer: D. If the NPV of a project is zero, then the IRR of the project will be equal to the discount rate for the project.
Explanation:
Net present value (NPV) refers to the difference that exist between the present value of the cash inflows and that of the cash outflows for a particular period of time.
The net present value is used in capital budgeting to determine if a projected investment or project will be profitable or not. For a project with normal cash flows, if the NPV of a project is zero, then the IRR of the project will be equal to the discount rate for the project.
Therefore, the correct option is D.