Answer:
Provided in Explanation
Explanation:
This is a very general question however I’ll try to answer it to the best of my knowledge.
If I use my own assumptions then these will be the Projections:
Selling Price $79.99 Selling Price $69.99
Cost of Sales/unit $40.00 Cost of Sales/unit $40.00
Expenses/unit $15.00 Expenses/unit $15.00
Demand @ $79.99 1000 Demand @ $69.99 1200
Sales $79,990.00 Sales $83,988.00
Cost of Sales $40,000.00 Cost of Sales $48,000.00
Expenses $15,000.00 Expenses $18,000.00
Profit $24,990.00 Profit $17,988.00
The final decision however relies on the Price Elasticity of the Product. If the Product is Price elastic then lowering the Price will lead to a significant rise in Demand. However if the Product is Price inelastic then lowering the Price will not lead to a significant rise in Demand and thus profit margins will be lowered. If the Product is Price inelastic then it is better to increase prices in order to gain more profits. In the case of Unit Elasticity the change in Demand will be at the same proportion as price change so it won’t be of any use to change the Price.
This process is called project management it leads a team or group of people with this process to achieve a goal they want or need to meet but sometimes at a certain time. I hope this helps!
Answer:
B)
Explanation:
Based on the information provided within the question it can be said that in this scenario you should preoxygenate him with a bag-mask device and then perform blind nasotracheal intubation. This is the process of placing oxygen tubes into the individuals nasal track and down the throat to allow better airflow.
Answer:
$65,000 Favorable
Explanation:
- Volume variance compute the difference due to volume of sales budgeted and actual sales qty.
- Budgeted Selling pricec =780000 /12000 = 65
- Sales volume variance = Budgeted Selling price (Actual sales qty-Budgeted Sales qty)
65.00 (13000-12000) = 65000 Fav
Answer is $ 65000 Favorable
Answer:
The correct answer is True.
Explanation:
The steps to follow to create a work breakdown structure are as follows:
1. Organize a meeting and share with the main stakeholders: team members are one of the most valuable assets in the process of creating the work breakdown structure. They have the knowledge, experience and creativity necessary to define each deliverable reaching the most specific details.
2. Complete the definition of all project deliverables: it is about going one step beyond the level reached in the planning and 100% complete the information on all project deliverables, including internal and external, associating each one with its estimated completion time.
3. Break down each deliverable into smaller, more manageable parts: it is about achieving a realistic level of work planning by the project manager, which ensures that, without interfering with the total estimated project deadline and the overall plan, it can be completed by the work teams. It is about determining work packages. These units constitute the lowest level of the EDT and are pieces of work that are specifically assigned to a person or a team of people to be completed, under the supervision of the Project Director. It is recommended that they focus on a single point of responsibility. The work packages will be used later to define the activities and tasks in which the project is divided.
4. Review the results obtained: with the stakeholders, both at the time of finalizing the elaboration of the work breakdown structure, and when modifications or updates are included, if applicable. It is essential to avoid overlaps.