Answer:
Sales quantity for A = $17,977
Sales quantity for B = $18,539
Sales quantity for C = $18,876
Explanation:
Given that
Monthly profit = $11,000
Fixed cost A = $5,000
Fixed cost B = $5,500
Fixed cost c = $5,800
The computation of given question is below:-
Every Sandwich Profit
= $2.65 - $1.76
= $0.89
Sales quantity = (Profit + Fixed cost) ÷ Profit per unit
Sales quantity for A = ($11,000 + $5,000) ÷ $0.89
= $17,977
Sales quantity for B = ($11,000 + $5,500) ÷ $0.89
= $18,539
Sales quantity for C = ($11,000 + $5,800) ÷ $0.89
= $18,876
Answer:
Total cost= $8,966
Explanation:
Giving the following information:
Direct materials $3,991
Direct labor-hours 85 labor-hours
Direct labor wage rate $13 per labor-hour
Machine-hours 129 machine-hours
The predetermined overhead rate is $30 per machine-hour.
The total cost is calculated as follow:
Total cost= direct material + direct labor + allocated overhead
Total cost= 3,991 + (85*13) + (129*30)
Total cost= $8,966
Answer:
The answer is 6.151%
Explanation:
The weighted average cost of capital (WACC) of the project is also the internal rate of return (IRR). The IRR formula is calculated by equating the sum of the present value of future cash flow less the initial investment to zero.