Answer:
a) You have found the critical path
Explanation:
The Time Cost Critical Path Method(CPM) in project management works by adding up/calculating duration of all tasks/activities in the project in order to find the longest time possible to complete the project. It is a method to estimate project duration using a flow chart that shows a network of tasks and estimated duration(start and finish times). The critical path is reached when project time is at the maximum/longest time of completion.
Answer:
The correct answer is : C. Neither breached the contract because there is no contract until Friday.
Explanation:
As the contract will only become valid when both the parties Mohan and ACME sign up and this will only happen on Friday. But as Mohan is informed by the Acme on Tuesday that they can not hire him before signing up the contract that is scheduled on Friday. Since there is no valid agreement between parties, no breach of contract occurred.
Thus, the correct answer is option C. Neither breached the contract because there is no contract until Friday.
Answer:
a) DM Windshield
(b) DM Engine
(c) DL Wages of assembly line worker
(d) MO Depreciation of factory machinery
(e) MO Factory Machinery lubricants
(f) DM Tires
(g) DL Steering wheel
(h) MO Salary of painting supervisor
Explanation:
Direct materials (DM) are those materials and supplies that are consumed during the manufacture of a product, and which are directly identified with that product.
Direct labor (DL) is production or services labor that is assigned to a specific product, cost center, or work order.
Manufacturing overhead (MO) is all indirect costs incurred during the production process.
(a) DM Windshield
(b) DM Engine
(c) DL Wages of assembly line worker
(d) MO Depreciation of factory machinery
(e) MO Factory Machinery lubricants
(f) DM Tires
(g) DL Steering wheel
(h) MO Salary of painting supervisor
A.
because as you're passing the page you are scanning it and looking for the answer