sold 500 tickets therefore it is not economically efficient
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
Normal profit is the return to the entrepreneur when the entire economic profits are equal to zero. Hence, the correct statement is Option A.
<h3>When the business earns normal profits?</h3>
A commercial enterprise may be in a state of normal profit while its economic income is equal to 0, that is why normal profit is also called “zero economic profit.” Normal profit takes place on the factor wherein all sources are being successfully used and could not be put to better use elsewhere.
Hence, Normal profit is the return to the entrepreneur when the entire economic profits are equal to zero. The correct statement is Option A.
learn more about Normal profit:
brainly.com/question/13800389
#SPJ1
Thomas Robert Malthus is the economist who supported it the most