Answer:
<u>Given :</u>
length offshore = CS=√(1+X^2)
Cable charged = 5000√(1+X^2)
onshore length = 4-X
laying cost = 3000(4-X)
total cost:
C=5000√(1+X^2) +3000(4-X)
DC/DX
= [5000*(0.5)*2X/{√(1+X^2)}]-3000=0... for optimum
5000X=3000√(1+X^2)
25X^2=3+3X^2
22X^2=3
X=√(3/22)
= 0.3693 miles
So, it would be laid offshore to S in a manner that
BS=X=0.3693 miles
Onshore=4-0.3693
=3.6307 miles
Answer:
i dont want to put the whole example cz like ur school might catch u so u gonna have to do the explainin part srry:( but the answear is 156$
Step-by-step explanation:
Answer:
24$
Step-by-step explanation:
$80 - $32 - $24 = $24