Program Evaluation and Review Technique (PERT) is a method used in program management. It analyzes the time required to complete each task in a project and so tries to determine the minimum time to complete a project. It was developed by the US Navy in 1957.
In PERT analysis:
- there are 3 time estimates for every activity: optimistic, pessimistic, and most likely
-
you have to find the Critical Path. The Critical Path is the longest path of scheduled activities that must be met in order to execute a project. It is important to know because any problems on the critical path can prevent a project from moving forward and be delayed. Therefore only critical activities can contribute to the project variance.
Answer:
6.80%
Explanation:
The average nominal returns is the sum of the returns for 5 years divided by the number of returns considered( i.e 5, 5 returns for 5 years)
average nominal returns=(6%-13%+24%+18%+15%)/5
average nominal returns=10.00%
The Fisher's equation is shown thus:
(1 + i) = (1 + r) (1 + π)
i=nominal return=10.00%
r=average real return=the unknown
π=inflation rate=3%
(1+10.00%)=(1+r)*(1+3%)
1.10=(1+r)*1.03
1+1=1.10/1.03
r=(1.10/1.03)-1
r=6.80%
Making decisions are always an important part. But failure in making decision may cause something unexpected. in most of the time a right decision at right time helps a lot... so for making a good decision one should follow some steps- like what are the good aspect if someone take this decision and what are the negative impact of this decision and if the probability of positiveness is more... than one should take that decision.. and if someone have confusion between what to do? and have to decide which decision to take among many ideas in mind one should do the same steps but this time he/she should write them in a page for each decision a single page and than take the one which is prominent..