Answer:
integer-4
proper fraction-1/10
improper fraction-0/4
Step-by-step explanation:
do not copy in the internet
Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Let's take the percentage as x
(x / 100) * 5 = 0.35
x / 100 = 0.07
x = 7
therefore the percentage is 7%
Answer:
319 miles.
Step-by-step explanation:
1.) Factor 9u^2-12u

2.) Cancel any common factors (in bold will be the terms eliminated)

Final answer is:
3u-4
Therefore, the answer is
C. 3u-4