Answer:
what do you mean by that
Explanation:
can you please explain more of the question
Answer:
Company Save $37000 by Buying
Explanation:
given data
make component part = 100 units
Direct Materials = $122000
Direct Labor = 34000
Variable Overhead = 55000
Fixed Overhead = 30000
purchase the component = $200000
fixed costs = $4000
to find out
make or buy decision
solution
first we find here Total Cost for Making component part
total cost = Direct Materials + Direct Labor + Variable Overhead + Fixed Overhead ..............1
put here value
total cost for make = $122000 + 34000 + 55000 + 30000
total cost for make = $241000
and
now we find here Total Cost for buying component part
total cost = Purchase Price + fixed costs ............2
put here value we get
total cost for buying = $200000 + $4000
total cost for buying = $204000
so
we can say Company Save = $241000 - $204000 = $37000 by Buying
Answer: Option B
Explanation: In simple words, top down approach refers to the approach ion which the organisation break down its system to have better and clear understanding of the sub systems within.
This approach is used by organisations doing complex business activities or involving high technical skills. Hence this approach is used by firms like biomedical ,financial services and high technology companies etc.
Im guess it would be 20,000 but im not positive