Answer:
10
Step-by-step explanation:
Acc to question, the workers have installed 240 chairs in 4 days which equals 60 chairs in 1 day.
So the will require 600 /60 =10 days from the start.
What ever solution is left over after solved
Https://www.youtube.com/watch?v=JnCYomYzJSw
this a youtube video that helped me when i needed to do it
Answer:
I believe the answer is 30.
Step-by-step explanation:
-