Answer:
2.20
Explanation:
The formula to compute the total assets turnover ratio is shown below:
Total asset turnover = (Sales revenue ÷ Total assets)
= ($670 ÷ $305)
= 2.20
We simply divide the sales revenue by the total assets, so that the total asset turnover ratio can be computed
All other information which is given is not relevant. Hence, ignored it
Answer:
a. $45.92 per equivalent unit
Explanation:
Calculation for direct material cost per equivalent unit
First step is to calculate the Total units
Total units = 2,500 + 500 - 800
Total units = 2,200
Now let calculate direct material cost per equivalent unit
Direct material cost per equivalent unit=($16,320+$121,440)/(2,200+$800)
Direct material cost per equivalent unit=$137,760/3,000
Direct material cost per equivalent unit=$45.92 per equivalent unit
Therefore the Direct material cost per equivalent unit will be $45.92 per equivalent unit
Answer:
The BCWS is also known as Planned Value (PV).
So, in this way, <em>PV = 3.125.000</em>
Explanation:
With the data we can obtain the PV as follows:
First, let's calculate EV as EV = CV + AC.
EV = -500.000 + 4.000.000 = <em>3.500.000</em>
After this, we can calculate PV with this formula: SPI = EV/PV
PV = EV/SPI
PV = 3.500.000/1.12 = <em>3.125.000</em>
<em />
<em>We can conclude, with these results, that the project actually is forward about the schedule but with an overcost about the budget. In other words, the project advance must be 41% but now is on 36% due to the negative variance on the costs (CV).</em>
<em />
Ensure your IBA is placed into PCS mission critical status.