fgiga [73]
3 years ago
14

For a project, the following earned value data have been assessed: AC: $ 4,000,000 CV: $ -500,000 SPI: 1.12 BAC: $ 9,650,000 Wha

t is the Planned Value (BCWS) of the project at the time of the assessment?
Business
1 answer:
Morgarella [4.7K]3 years ago
7 0

Answer:

The BCWS is also known as Planned Value (PV).

So, in this way, <em>PV = 3.125.000</em>

Explanation:

With the data we can obtain the PV as follows:

First, let's calculate EV as EV = CV + AC.

EV = -500.000 + 4.000.000 = <em>3.500.000</em>

After this, we can calculate PV with this formula: SPI = EV/PV

PV = EV/SPI

PV = 3.500.000/1.12 = <em>3.125.000</em>

<em />

<em>We can conclude, with these results, that the project actually is forward about the schedule but with an overcost about the budget. In other words, the project advance must be 41%  but now is on 36% due to the negative variance on the costs (CV).</em>

<em />

You might be interested in
In an organization in which high-level managers make the effort to involve others in decision making and seek opinions of others
NNADVOKAT [17]

Answer:

People or team oriented

Explanation:

The best organization culture is there when there is no comparison between the people who are working at different departments, different levels, etc

The rules, procedures, policies are all not for any single person

Here if the high level managers involves the others in decision making process and seek their opinions for the betterment of an organization that this represents the team oriented as the whole organization is working as a team so the same is to be considered

7 0
3 years ago
Greg Jewell read about several companies that were performing relatively well despite the current recession. Stocks like these,
poizon [28]

Answer:

C) defensive

Explanation:

Defensive stocks are stocks that generally perform well during economic recessions. In other words, their price is not related to the market tendency. Even if the market goes down, their price remains stable. Generally companies that sell products with a constant demand are considered defensive stocks, e.g. Costco, Target, Walmart, utilities (all, electric, gas, water), etc.

7 0
4 years ago
Penny Lyman is the owner and operator of Go109, a motivational consulting business. At the end of its accounting period, Decembe
zalisa [80]

Based on the accounting equation, the amount for each case can be independently determined as follows:

a. The Penny Lyman, capital, as of December 31, 20Y1, is <u>$494,000.</u>

b. If assets increased by $88,000 and liabilities increased by $27,000, the Penny Layman, capital, as of December 31, 20Y2, is <u>$555,000</u>.

c. If assets decreased by $151,000 and liabilities increased by $13,000, the Penny Layman, capital, as of December 31, 20Y2, is <u>$330,000</u>.

d. If assets increased by $152,000 and liabilities decreased by $16,000 during 20Y2, the Penny Layman, capital, as of December 31, 20Y2, is <u>$672,000</u>.

e. Assuming that as of December 31, 20Y2, assets were $782,000, liabilities were $196,000, and there were no additional investments or withdrawals, and the capital remained $494,000 of 20Y1, then the net income or (loss) for 20Y2 is <u>$92,000</u> ($782,000 - $196,000 - $494,000)

<h3>Data and Calculations:</h3>

Assets at December 31, 20Y1 =$659,000

Liabilities = $165,000

Capital = Assets - Liabilities

= $494,000 ($659,000 - $165,000)

<h3>20Y2:</h3>

Assets = $747,000 ($659,000 + $88,000)

Liabilities = $192,000 ($165,000 + $27,000)

Capital = $555,000 ($747,000 - $192,000)

<h3>Question C:</h3>

Assets = $508,000 ($659,000 - $151,000)

Liabilities = $178,000 ($165,000 + $13,000)

Capital = $330,000 ($508,000 - $178,000)

<h3>Question d:</h3>

Assets = $821,000 ($659,000 + $162,000)

Liabilities = $149,000 ($165,000 - $16,000)

Capital = $672,000 ($821,000 - $149,000)

<h3>Question Completion:</h3>

a. Penny Lyman, capital, as of December 31, 20Y1. $

b. Penny Lyman, capital, as of December 31, 20Y2, assuming that assets increased by $88,000 and liabilities increased by $27,000 during 20Y2. $

c. Penny Lyman, capital, as of December 31, 20Y2, assuming that assets decreased by $151,000 and liabilities increased by $13,000 during 20Y2. $

d. Penny Lyman, capital, as of December 31, 20Y2, assuming that assets increased by $152,000 and liabilities decreased by $16,000 during 20Y2.

e. Net income (or net loss) during 20Y2, assuming that as of December 31, 20Y2, assets were $782,000, liabilities were $196,000, and there were no additional investments or withdrawals.

Learn more about the accounting equation here: brainly.com/question/24401217

3 0
2 years ago
A company has developed a new smart clock. If the clock is successful, the present value of the payoff (at the time the product
timama [110]
The correct answer is letter C
5 0
3 years ago
A __________ is a type of purchasing contract in which the price of a good or service is tied to the cost of some key input(s) o
Sonbull [250]

Answer:

Cost-based contract

Explanation:

A cost-based contract is tied to various factors which can change the overall price of a good or service. Likewise, the only difference between the cost-based contract and the fixed-price contract is the change in the price during the contract. A price can change in a cost-based contract because of inputs and economic factors such as exchange rate or interest rate.

6 0
4 years ago
Read 2 more answers
Other questions:
  • F the goods' money prices do NOT change, an appreciation of the dollar against the pound
    7·1 answer
  • The president of a growing engineering firm wishes to give each of 20 employees a holiday bonus. how much needs to be deposited
    5·1 answer
  • Which protist produces its own food but is apparently unable to move on its own?
    8·1 answer
  • The 2017 balance sheet of Kerber's Tennis Shop, Inc., showed long-term debt of $6.3 million, and the 2018 balance sheet showed l
    15·1 answer
  • ​Virginia's Ron McPherson Electronics Corporation retains a service crew to repair machine breakdowns that occur on an average o
    7·1 answer
  • During 2021, Deluxe Leather Goods issued 707,000 coupons which entitles the customer to a $5.00 cash refund when the coupon is s
    12·1 answer
  • In your own words, discuss GAP management and then suggest a way to reduce the impact of its limitation. Do not duplicate limita
    12·1 answer
  • Identify two examples of businesses that operate in the secondary sector
    6·1 answer
  • The following information is taken from the production budget for the first quarter: Beginning inventory in units 1,200 Sales bu
    10·1 answer
  • Which of the following account should not be entered in the debit side of the Trial balance?
    8·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!