Answer:
Jim's path is the critical path on this activity graph.
Step-by-step explanation:
Critical Path:
Critical path is the the longest path in the project task paths. It shows the least amount of time in which project can be completed. It can be find by looking at the longest path in the network diagram of the project; not in term of nodes or activities instead in term of days.
In given case:
Path 1 Bill task's total duration= 6 days
Path 2 Jim's task's total duration= 17 days
Path 3 Betty task's total duration= 7 days
Path 4 Cynthia task's total duration= 14 days
Hence the longest path i.e. critical path is of Jim's activity path !
Answer:
20 possible outcomes
Step-by-step explanation:
5 equal-sized sections x 4 sides of the die = 20
Answer:
The answer is 44.
Step-by-step explanation:
Answer:
The length and width of the parking lot is 78 meters and 114 meters respectively.
Step-by-step explanation:
Given;
Perimeter of the parking lot = 
Solution,
Let the width of the parking lot be x.
Then, according to question length = (x-36).
The perimeter of a rectangle is sum of all the sides of rectangle. Which is given by an expression;

Now substituting the values, we get;

Width = 
Length = 
Hence the length and width of the parking lot is 78 meters and 114 meters respectively.
Answer:
B.
Step-by-step explanation:
You can't have the same X values for two different Y values
in this case 19 goes with 11 and 10 in the pairs (19,11) and (19,10)