Answer:
16 workers are required to complete the work in 45 days...
Step-by-step explanation:
12 workers are required to complete the work in 60 days
so... 60*12=720 workers are required to complete the work in 1 day
Hence,
720/45 = 16 workers are required to complete the work in 45 days.
Answer:
Approximately 2 months
Step-by-step explanation:
Tricia: f(d) = 5.15m + 10.25
Melanie: f(d) = 10.25m
f(d) is the total savings altogether
m is the amount of months
5.15(2) + 10.25 = 20.55
10.25(2) = 20.50
They will have the same amount of savings in approximately 2 months
1.990291 is the actual time (in months) they will be the same
Answer:
tysm bro
Step-by-step explanation:
Answer:
y=-2x+3
Step-by-step explanation:
Answer:
3150 inches is the volume
Step-by-step explanation:
i hoped this helped