1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
denis23 [38]
3 years ago
13

I need help ASAP!

Mathematics
1 answer:
Semmy [17]3 years ago
5 0

Answer:

One angle measures 150 degrees.

The second angle is 30 degrees.

Step-by-step explanation:

You might be interested in
2(s + 3) = 4s - 5<br><br> Can you help me find s?
Anastasy [175]
2(s+3)=4s-5
2s+6=4s-5
4s-2s=5+6
2s=11
s=5,5
5 0
3 years ago
Using the Binomial Probability table, find P(X) when n = 7, X &lt; 3, and p = 0.5 A. 0.273 B. 0.500 C. 0.227 D. 0.773
Nat2105 [25]

Answer:

0.227

Step-by-step explanation:

Given that X is binomial with n=7 and p =0.5

To find the probability for P(X<3)

i.e. we have to find prob as =P(x=0,1,2)

=P(X=0)+P(X=1)+P(x=2)

P(X=r)=7Cr(0.5)^7

Using binomial table we find prob

P(X<3)=0.2265

Round off this to 3 decimals as

0.227

Hence answer is 0.227

8 0
3 years ago
HELP PLS I NEED A ANSWER NOW IT IS DUE TODAY
san4es73 [151]

Answer:

you need to find how many pencils the teacher needs for the class

Step-by-step explanation:

6 0
3 years ago
Read 2 more answers
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minute
Maurinko [17]

Answer:

Minimum cycle time = time for longest task = 2.4 minutes

Maximum cycle time = sum of the times to complete all the tasks = 18 minutes

Step-by-step explanation:

For the minimum cycle time, the reasoning is that all the tasks can be done simultaneously, at some during the assembling task. Hence, minimum time to complete one cycle is the time it takes to complete task that takes the longest time to complete.

For the maximum cycle time, the reasoning here is that each task is done after the completion of the previous task. The total time taken to finish the task will then be the sum of the time taken to complete each task. This usually is at the beginning of operations.

6 0
3 years ago
Three houses are mapped on a coordinate grid. Joshs house is located on red street at (-5,-4). Sarah’s House is located on green
vlada-n [284]

Answer: 90

Step-by-step explanation:

5 0
3 years ago
Other questions:
  • Thirteen less than eight times a number is equal to 11 more than six times the number
    12·1 answer
  • Which ordered pairs are solutions to the inequality 2x+y&gt;−4?
    15·1 answer
  • You bought a 5 pound turkey for 14.45. How much would a 7 pound turkey cost?
    15·2 answers
  • Write the definition of a class Clock. The class has three instance variables: One of type int called hours, another of type boo
    11·1 answer
  • What is the volume of a cylinder? Give an informal argument for the formula.
    5·2 answers
  • X-2&gt;2x+12 <br> solve for x
    9·1 answer
  • Can someone check my work?
    9·2 answers
  • True or false? help please
    12·2 answers
  • Omar painted half of a heart on a piece of paper.
    5·1 answer
  • Equation for the line that passes through (4,7) and is perpendicular to the line Y= 2/3x-1
    9·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!