Answer:
The answer is "Option d".
Explanation:
The Iteration Management is also an activity in which all members of the team will determine how many the backlog team will allocate towards the next Iteration, and each team wraps up the work only as a group of determined iteration targets. in the given question the "choice d" is correct because The plans to achieve without training entered PO or design staff and requirements have not even been identified, and the wrong choice can be defined as follows:
- In choice A, T' he PO doesn't give the story detail, that's why it's incorrect.
- In choice B, the doesn't a team left the past for more refining with the PO in the Project Backlog, that's why it's incorrect.
- In choice C, The Development Team has not found some other team dependency, that's why it's incorrect.
Answer:
Answer in the below
Explanation:
Redo means the previous one and undo means removing it... i am not so sure..
Answer:
Check the explanation
Explanation:
Here is the program with function definition and two sample calls.
Code:
#include <iostream>
using namespace std;
//checkMe FUNCTION which takes values a, b and c
void checkMe(char &a, int &b, int &c)
{
//if sum of b and c is negative and a is 'n', b and c are set to 0, otherwise a is set to 'p'
if((b+c)<0 && a=='n')
{
b = 0;
c = 0;
}
else
{
a = 'p';
}
}
int main()
{
//first test case when else part is executed
char a = 'n';
int b = 5;
int c = 6;
checkMe(a, b, c);
cout<<a<<" "<<b<<" "<<c<<endl;
//second test case when if part is executed
a = 'n';
b = -4;
c = -5;
checkMe(a, b, c);
cout<<a<<" "<<b<<" "<<c<<endl;
return 0;
}
Kindly check the Output below: