The value-added percentage of the flow time for this bike frame is:
= 46.
Explanation:
a) Data and Calculations:
Bike Frame Flow Time:
Setup time = 7 hours
Processing time = 6 hours
Storage time = 7 hours
Flow time of the bike frame = 13 hours (7 + 6)
Value-added percentage of the flow time for this bike frame = 6/13 * 100
= 46%
b) Flow time represents the amount of time a bicycle frame spends in the manufacturing process from setup to end. It is called the total processing time. Unless there is one path through the process, the flow time equals the length of the longest process path. The storage time is not included in the flow time since it is not a manufacturing process.
Answer:
when someone answers your questio correctly, you will see a red crown. Click on that and mark them the most brainiest
Explanation:
Answer:
Following are the solution to the given point:
Explanation:
The solution to this question is defined in the attached in the attached file.