Answer:
Risks of the project include
disruption in the highway during renovation process. - High risk
Poor material used in the construction - High risk
Rainfall may delay the work process. - Medium risk
Traffic flow management will be difficult during peak hours. - Medium risk
Dust and noise during the construction will disturb the society. - Low risk
Explanation:
The risk register includes Risk description, its impact in terms of probability and measures to mitigate such risk. There are many potential risks that are associated with the construction of the bus shelter. The risks are not acceptable as the highway disruption should be kept to minimum and any delay in the work is not tolerable. These risks are reduced by deploying extra labors so that the renovation work is completed on time.
Answer:
If the economy is at the potential output and the Fed increases the money supply, in the long run real GDP will likely remain the same.
Explanation:
hoped this helped
Answer:
d
Explanation:
electronica means electronic. i hope i helped u, have a nice dat
Answer:
The correct answer is option (a).
Explanation:
According to the scenario, computation of the given data are as follows:
Allowance method shows that, if account is written off, then Accounts receivable account gets credited and Allowance accounts gets debited.
Here, both accounts are or balance sheet items.
So, it will not affect any expenses account.
Answer:
Standard cost per unit= $282.6
Explanation:
Giving the following information:
Direct materials per unit: 3.00 pounds at $4.20 per pound
Direct labor per unit: 9.00 hours at $12 per hour
Manufacturing overhead: Allocated based on direct labor hours at a predetermined rate of $18.00 per direct labor hour
The standard cost per unit is the sum of direct material. direct labor, and allocated overhead:
Standard cost per unit= 3*4.2 + 9*12 + 9*18
Standard cost per unit= $282.6