Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
There are 6 dimes and 9 quarters.
Step-by-step explanation:
Represent the number of dimes and the number of quarters by d and q.
Then d + q = 15, or q = 15 - d.
Also, ($0.25)q + ($0.10)d = $2.85, or 5q + 2d = 57.
Substituding 15 - d for q, we get 5(15 - d) + 2d = 57, or
75 - 5d + 2d = 57, or
75 - 3d = 57, or
3d = 18. Thus, there are 6 dimes. Since q = 15 - d, q = 15 - 6 = 9.
There are 6 dimes and 9 quarters.
Answer:
X < -1
Step-by-step explanation:
4x - 5 + X < -10
5x < -5
× < -1
hundred means 100 or 200. Like I have 100 cats.
Hundredth means you have 1/100 of something. I have a peice of pie that is 1/100 of the pie. That means there are 100 pieces of the pie but I only have one out the hundred pieces.
hundred=100
hundredth = 1/100 = 0.01
tenth= 1/10 = 0.1