O=4i (is that was you were asking about)
edit: sorry that wasn't very detailed say if the input is 4 the output will be 16 or if the input is 100 the output will be 400. So mainly what ever the input is multiply it by 4.
I hope this helps :)
Answer:
13.5
Step-by-step explanation:
the two medians are 12 and 15. you need to then find the average. 12+15=27. 27/2=13.5.
10 because 7 x 3 = 21 and 7 + 3 = 10 so your answer is 10
Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.