Answer:
Value of S=$25000.
Explanation:
Value of P= $75000
Value of n= 5 years
Value of AOC= $36000+ $1500k (k=1 to 5)
Since the salvage value would be after 5 years=
S=($75000- $10000*5) = $75000- $50000= $25000.
Value of S=$25000.
Answer:
Interest payment on bonds payable is a cash outflow from financing activities.
Explanation:
The only statement which is false from the list is : Interest payment on bonds payable is a cash outflow from financing activities.
Interest payment on bonds payable is an expense in the income statement used to determine the income for the year. Net Income falls under the Cash flows from Operating Activities.
Answer: 9.04%
Explanation:
1 year rate today = 5% = 0.05
2 years rate today = 7% = 0.07
Maturity of longer bond = 2
The ending return if the 2 years bond are bought will be thesame as the needed return on series of a year bond which will be 1.1449
The market's forecast for 1-year rates 1 year from now will be calculated as:
= 1.05(1+X) = 1.1449
1.05 + 1.05X = 1.1449
1.05X = 1.1449 - 1.05
1.05X = 0.0949
X = 0.0949/1.05
X = 0.090381
X = 9.04%
Answer:
$10,883
Explanation:
n = 31 years
Future value (FV) = 1,980,000 (The amount you need in 31 years for retirement)
i/r = 10% (given)
Present value (PV) = 0 (You have just started your job and have not reserved any amounts for retirement)
PMT (Monthly deposit needed) = ?
By using financial calculator, PMT = $10,883
Answer:
True
Explanation:
the process of identifying and defining what actions are required to deliver a project's requirements