According to the investment model there should be a degree of satisfaction in the relationship to have stability. But Dave doesn't have that commitment which means he is not satisfied with his relationship. This led him to be attracted with other women he worked with. He felt that these women showed interest to him and he thought of this can be the opportunity to find someone else. This is his alternative to find satisfaction that he is looking for.
Answer:
$17.97 per unit
Explanation:
Using weighted average method, Equivalent units = Units that are completed during the period + Equivalent units in process at the end of period.
Equivalent units = 8,500 + 2,000*90%
Equivalent units = 8,500 + 1,800
Equivalent units = 10,300
Cost per equivalent unit for materials = (Beginning costs + Current costs) / Equivalent units
Cost per equivalent unit for materials = ($13,000 + $172,100) / 10,300 units
Cost per equivalent unit for materials = $185,100 / 10,300 units
Cost per equivalent unit for materials = $17.97 per unit
Answer: D) Favorable Unfavorable
Explanation:
To begin, it is worthy of note that in Variance, if something is said to be Favourable, it means a negative Variance because less resources than planned were spent. When it is Unfavourable, it means a positive balance variance.
Now, The formula for Labour Rate Variance is as follows,
LABOUR RATE VARIANCE=(ACTUAL RATE-STANDARD RATE)*ACTUAL HOURS WORKED
Seeing as the old workers were being paid $18, and the new office ones were paid $10, we can see that to be the actual rate was less than the standard rate. This would mean that there was a FAVOURABLE balance.
Labour Efficiency is calculated in a similar way,
LABOUR EFFICIENCY VARIANCE=(ACTUAL HOURS WORKED-STANDARD HOURS)*STANDARD RATE.
Now, these are Office workers not assemblyline workers. They do not have the experience to work in such a way that they produce as fast or as efficiently as their striking Assemblyline colleagues.
This would then mean that their actual hours will be MORE than the standard rate which can only lead to an UNFAVOURABLE BALANCE.
Answer:
D. All of the answers are correct.
Explanation:
Given that Variance Analysis is a form of measuring and controlling methods used by a business management team to maintain and monitor the firm's planned cost and sales with the eventual outcome of cost spent and sales generated.
To achieve this, the process helps in determining the disparity between the actual costs of budgeted costs.
It also helps them to know which department is more productive and
It also helps to discover where the problems or difficulties exist in the production process
Hence, in this case, the correct answer is option D, All of the above. Because the option A to C satisfies the answer.