Answer:
It would take
or <u>4.24 hours</u> to oil the lanes if they work together.
Step-by-step explanation:
Given:
Time to oil the lanes by Jimmy alone = 8 hours
Time to oil the lanes by Perry alone = 9 hours
Now, let the time taken by both working together be 'x' hours.
Part of the work done in 1 hour by Jimmy alone = 
Part of the work done in 1 hour by Perry alone = 
Part of the work done in 1 hour by Jimmy+Perry together = 
Now, total work in 1 hour is given as:

Therefore, it would take
or 4.24 hours to oil the lanes if they work together.