Daniel [21]
3 years ago
13

All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:

Business
1 answer:
Elodia [21]3 years ago
6 0

Answer:

Correct answer is (a). adding a significant buffer to each activity

Explanation:

Realistic time estimates for project is an essential skill required by project management team to estimate required time for a component or whole project to be completed. It is expressed in person hour. Adding a significant buffer to each activity in project management does not required by team to estimate the time required to complete project.

You might be interested in
. Zoe Corporation has the following information for the month of March: Purchases $ 92,000 Materials inventory, March 1 6,000 Ma
rodikova [14]

Answer:

1. Cost of goods manufactured = $150,500

2. Net income = $36,500

3. Total Inventory = $61,500

Explanation:

Requirement 1

                   Zoe Corporation

Schedule of cost of goods manufactured

     For the month ended March 31

Direct Materials:

Beginning Materials inventory             $6,000

Add: Raw materials purchases         <u>    92,000</u>

Raw materials available for use          $98,000

<u>Less: Ending Raw Materials                    8,000</u>

Direct materials used                          $90,000    

<u>Direct Labor                                           25,000</u>

Prime Cost                                          $115,000

<u>Factory overhead                                   37,000</u>

Total manufacturing cost                 $152,000

Add: Work in process, March 1              22,000

<u>Less: Work in process, March 31          (23,500)</u>

Cost of goods manufactured           $150,500

Requirement 2

                        Zoe Corporation

Income Statement for manufacturing company

            For the month ended March 31

Sales revenue                                                                $257,000

<em>Less: Cost of goods sold</em>

Beginning finished goods inventory           $   21,000

Add: Cost of goods manufactured (Req.1)   <u>  150,500</u>

<em>Finished goods available for sale                   171,500</em>

Less: Ending finished goods inventory     <u>     (30,000)</u>

<u>Cost of goods sold                                                            141,500</u>

Gross Profit                                                                     $115,500

<u>Less: Sales and administrative expenses                         79,000</u>

Net operating Income                                                    $36,500

Requirement 3

                        Zoe Corporation

                          Balance Sheet

                          As at March 31

Inventory:

Materials                           $8,000

Work-in-process               23,500

<u>Finished goods                 30,000</u>

Total Inventory                $61,500

Inventory consists of all the ending materials, ending work-in-process, and ending finished goods. All the ending items need to be shown in the balance sheet because those inventories will remain at hand at the end of the period.

5 0
3 years ago
When the cost minimizing combination of inputs is being used and there is no corner​ solution,
LenKa [72]

Answer:

A. the iso-quant line is tangent to the iso-cost line.

Explanation:

Cost minimization refers to the decrease in level of cost of production for certain specified level of production.

Iso quant line represents the labor and capital combinations keeping the total cost same. The least combination represents the tangent to isoquant, basically representing the idle choice of labor and capital.

In this manner the company chooses the idle way of cost minimization.

4 0
3 years ago
Supply of Children's Books Price (dollars) Quantity (books) $12 24 10 20 8 16 6 12 4 8 2 4 0 0 Instructions: Round your answers
Nataly_w [17]

Answer:

40%

Explanation:

the percentage change in price using the midpoint method = {(P₂ - P₁) / [(P₂ + P₁)/2]} x 100

= {($6- $4) / [($6 + $4)/2]} x 100 = [$2 / ($10 / 2)] x 100 = ($2 / $5) x 100 = 0.4 x 100 = 40%

The advantage of using the midpoint method for calculating percentage changes is that it doesn't matter if the change is positive or negative, e.g. it will yield the same result if the price increases or decreases in the same amounts.

5 0
3 years ago
"An automotive company was looking to expand internationally and selected three possible countries in which to build a factory.
zheka24 [161]

Answer: bribery and conflict of interest

                   

Explanation: In simple words, bribery refers to the act under which one individual tries to persuade the behavior of another individual for his benefit  by offering him or her monetary benefits.

Whereas, conflict of interest refers to a situation when someone has the authority to make decisions that benefits himself more than the entity he is working for.

Hence we can conclude that the above case depicts bribery and conflict of interest.

8 0
3 years ago
For the cost and price functions below, find
murzikaleks [220]

Answer:

a) The number, q, of units that produces maximum profit = 15

b) The price, p, per unit that produces maximum profit = 47 (currency not giben in the question)

c) Maximum Profit = P = 380 (currency not given in the question).

Explanation:

The cost function and price per unit function are given respectively as

C(q) = 70 + 17q

p = 77 - 2q

where q = quantity or number of units

a.) the number, q, of units that produces maximum profit

Total cost = C(q) = 70 + 17q

Revenue = (price per unit) × (Number of units) = p × q = (77 - 2q) × q = (77q - 2q²)

Profits = P(q) = (Revenue) - (Total Cost)

P(q) = (77q - 2q²) - (70 + 17q)

P(q) = -2q² + 60q - 70

To maximize the profits, we just obtain the point where the profit function reaches a Maximum.

At the maximum of a function, (dP/dq) = 0 and (d²P/dq²) < 0

Profit = P(q) = -2q² + 60q - 70

(dP/dq) = -4q + 60

At maximum point,

(dP/dq) = -4q + 60 = 0

q = (60/4) = 15

(d²P/dQ²) = -4 < 0 (hence, showing that the this point corresponds to a maximum point truly)

Hence, the number, q, of units that produces maximum profit = 15.

b.) the price, p, per unit that produces maximum profit

The price per unit is given as

p = 77 - 2q

Maximum profit occurs at q = 15

p = 77 - (2×15) = 47

Hence, the price, p, per unit that produces maximum profit = 47 (currency not given in the question)

c.) the maximum profit, P.

The Profit function is given as

Profit = P(q) = -2q² + 60q - 70

At maximum Profit, q = 15

Maximum Profit = P(15)

= -2(15²) + 60(15) - 70

= 380 (currency not given in the question).

Hope this Helps!!!

8 0
3 years ago
Other questions:
  • Which of the following is not a feature or characteristic of subscription monitoring tools? Select one: a. Most moderate and hig
    9·1 answer
  • Shelby's new job with the federal government provides a comfortable income and a fairly stable income. she would like to buy a n
    6·1 answer
  • What is the primary task of the Federal Reserve​
    9·2 answers
  • Which of the following tasks would most likely be the responsibility of middle management?
    9·1 answer
  • During June, Buttrey Corporation incurred $86,000 of direct labor costs and $26,000 of indirect labor costs. The journal entry t
    12·1 answer
  • The straight-line depreciation method and the double-declining-balance depreciation method: Multiple Choice Are acceptable for t
    5·1 answer
  • Br.uh + meme =jhhbn b bbv v
    15·2 answers
  • Introduce national employment with its importance and examples​
    9·1 answer
  • Mrs. Hanson has 2 pies for a party. She calculates that if she splits the pies evenly among the guests, they will each receive
    7·1 answer
  • Emily Corporation has an employee benefit plan for compensated absences that gives each employee 15 paid vacation days. Vacation
    14·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!