Answer:
Cash Balance at the beginning of the year = $4,600
Explanation:
Opening Cash Balance = Closing Cash Balance - Net Increase (Decrease) in Cash
Opening Cash Balance = $18,100 - $13,500 = $4,600
Answer:
a) the leader presents ideas and invites questions.
Explanation:
Leadership continuum is a leadership style which describes the relationship with respect to the autonomy that a manager gives to his subordinates, and the level of authority used by him/ her. This is a inverse proportional relation which reduces the authority of the manager when team's freedom increases. It debases an autocratic rule by a manager, especially in taking decisions.
The example cited in the question is a way of taking decision by suggestions by expecting questions from his team.
Answer:
Option d (increase.....................transportation) seems to be the right option.
Explanation:
- This same fourth phase throughout the past decades of U.S. regulatory requirements started throughout the late 1970s as well as focuses primarily on industrial protectionism.
- Throughout that stage of development, the current regime has focused on increasing competitive advantage throughout sectors such as construction, utility services, transshipment as well as wealth management by deactivating an amount of regulation but rather allowing companies to diversify their business processes to developing companies.
The interpretation of that same question has been characterized throughout the explanation paragraph below.
<span>When it is reported that a nation is experiencing a "balance of payments deficit," this is best interpreted to mean that the nation is experiencing? If it is reported that the nation is experiencing a balance of payments deific, the country is importing more goods, services and capital than it is exporting. When this happens, the nation has to borrow funds and items from other countries to help pay for what they are importing until the have the cash funds to pay for them, themselves. When this starts the happen, the nation that this is hurting should try and balance their payments and monitor transactions better to eliminate this in the future. </span>
Answer: 0.8186
Explanation:
Given that;
activity To Tm Tp Te (V)^0.5 v
A 38 50 62 50 4 16
B 90 99 108 99 3 9
C 70 80 90 80 3.333333 11.11111
D 19 25 31 25 2 4
E 91 100 115 101 4 16
F 62 65 68 65 1 1
Expected duration Te = (4 × Tm + To + Tp ) / 6
Variance = ( Tp-To/6]²
variance of the critical path = 9+16 =25
SD of the critical path = ( var)^0.5 = 5
probability that the project will be completed within 210 days is given by
z = (210-200) / 5 = 2
which gives probability of 0.97725
Probability that the project will be completed within 195 days
z = (195-200) / 5 = -1
which corresponds to probability of 0.1586
Now required probability that project completes within 210 but before 195 days is given by
0.97725 - 0.1586 = 0.8186