Answer:
C. Correct, because for the work to be carried out in 5 days, 40 workers are required.
Step-by-step explanation:
The job requires 10 people to work for 20 days. That's 200 worker-days.
In other words,
days × workers = 200 or
workers = 200/days
To get the work done in five days,
workers = 200/5 = 40.
You must hire 40 workers.
B. and D. are wrong. To get the job done in seven days. you must hire 200/7 = 29 workers.
Answer:
5 hours
Step-by-step explanation:
Divide 275/55 to equal 5
I believe it is 1.5 pounds each as 13 1/2=13.5
13.5/9=1.5
Answer
600
Step-by-step explanation:
ur welcome kid!!!!!!!!!!