Answer:
11.00
Explanation:

36,000 net income
200,000 common stock / $4 per share= 50,000 shares
36,000 / 50,000 = 0.72 earnings per share

7.92 / 0.72 = 11
Answer:
The correct answer is A.
Explanation:
Giving the following information:
Refurbishing materials:
Variable cost= $600
Fixed costs= $18,800
Estimated cost= 600*35 + 18,800= $39,800
Actual cost= 600*32 + 18,800= $38,000
Refurbishing activity variance= Estimated - actual cost
Refurbishing activity variance= 39,800 - 38,000= 1,800 favorable
Answer:
Risks of the project include
disruption in the highway during renovation process. - High risk
Poor material used in the construction - High risk
Rainfall may delay the work process. - Medium risk
Traffic flow management will be difficult during peak hours. - Medium risk
Dust and noise during the construction will disturb the society. - Low risk
Explanation:
The risk register includes Risk description, its impact in terms of probability and measures to mitigate such risk. There are many potential risks that are associated with the construction of the bus shelter. The risks are not acceptable as the highway disruption should be kept to minimum and any delay in the work is not tolerable. These risks are reduced by deploying extra labors so that the renovation work is completed on time.
Answer:
B
Explanation:
moneys always good motivation
The answer is C because it’s decided by who owns the production.