Total labor content is 4.2143 min per shirt.
<h3>What do you mean by labor content?</h3>
The sum of all the process stages' individual times is known as the total labor content. For instance, if a procedure has two steps that each take 20 seconds, the total labor time is 40 seconds. Cycle time minus processing time is the definition of idle time.
Capacity of resource 1=35 shirts / hour
Time taken per shirt at resource 1=60 / 35=1.7143 minutes
Capacity of resource 2=24 shirts / hour
Time taken per shirt at resource 2=60 / 24=2.5 minutes
Therefore,
Total labor content = Time taken per shirt at resource 1+ Time taken per shirt at resource 2=1.7143+2.5=4.2143 minutes per shirt
Disclaimer
Shirts are made in a process with two resources. There is one worker in eachresource. The first resource has a capacity of 35 shirts per hour. The capacity of thesecond resource is 24 shirts per hour. Demand for this process is 20 shirts per hour. What is the total labor content in a shirt? Provide your answer in minutes per shirt.
Learn more about labor content here
brainly.com/question/28059667
#SPJ1
Answer:
True
Explanation:
Exceptionally good weather will guarantee a good yield in crops. This will lead to an increase in supply of produce to the market, and when supply increases, the supply curve shifts to the right.
This is simply because there are more products and more sellers, and this will result in more supply.
Answer:
a. $ 2.8 million
Explanation:
Calculation to determine what The regret associated with the alternate decision would be
Using this formula
Regret associate=Payoff for best decision alternative - Payoff for one of the other alternatives
Let plug in the formula
Regret associate= $15.7million - $12.9million
Regret associate= $2.8million
Therefore The regret associated with the alternate decision is $2.8million.
Explanation:
D.
the time during which a workflow is interrupted