Answer: (D) Accept the risk
Explanation:
According to the given question, the one of the best solution is to accept the risk as the 2 given risks in the project cannot be removed or also outsourced from the given project scope.
Accepting the risk is one of the risk retention process in which we sometimes cannot avoid the given risk in the risk management and it is commonly found in the various types of investment process and also in the business.
On the basis of the given scenario, we could not eliminate the two risks in the project so the best solution is to using the risk acknowledgement due to some limitations. Therefore, Option (D) is correct answer.
Answer: d. Entire initial investment will not be recovered.
Explanation:
The Payback period by definition is the amount of time it will take a Project to recover the initial investment into it. For example, if a project had an investment of $20 million and made $5 million every year, the Payback period would be 4 years.
Now, if the amount of time it will take to recover an investment is longer than the expected amount of time the project will run (expected useful life) then logically speaking that would mean that the Investment would not be entirely recovered because the project will be done before it can pay off the investment hence Option D is correct.
Assuming the user took advantage of this offer, the amount that would be discounted on a $10,000 invoice is: $200.
<h3>
Discounted amount </h3>
Using this formula
Discounted amount =Discount rate× Invoice
Let plug in the formula
Discounted amount=2%×$10,000
Discounted amount=$200
Therefore assuming the user took advantage of this offer, the amount that would be discounted on a $10,000 invoice is: $200.
Learn more about Discounted amount here:brainly.com/question/12965533
#SPJ1
To increase the usage of the road the community should stop collecting toll payment, that is, they should set the toll equal to zero.
Answer:
Developing an action plan once the process has started
Explanation: