Answer:
Results are below.
Explanation:
Giving the following information:
Month Number of instruments used Total autoclave cost
January 634 $7,466
February 534 6,526
March 734 7,148
April 934 9,028
May 834 7,744
June 1,034 8,596
July 1,234 10,009
August 1,134 9,924
<u>To determine the fixed and variable cost, we need to use the high-low method:</u>
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (10,009 - 6,526) / (1,234 - 534 )
Variable cost per unit= $4.9757 per unit
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 10,009 - (4.9757*1,234)
Fixed costs= $3,869
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 6,526 - (4.9757*534)
Fixed costs= $3,869
Total cost= 3,869 + 4.9757x
x= number of instruments
Answer:
The correct answer is letter "B": nonphysical constraints.
Explanation:
According to the Theory of Constraints (TOC) a constraint is a limiting factor that does not enable companies to perform their work at their maximum capacity for their goals' achievement. In the same sense, nonphysical constraints are not material factors negatively influencing employees' actions. Wages cuts, reduction of benefits, unclear lines of command are examples of that kind of constraint.
Answer:
Direct material= $5,600
Explanation:
<u>First, we need to calculate the direct labor added to Work in Process:</u>
Direct labor= allocated overhead / predetermined overhead rate
Direct labor= 6,400 / 0.8
Direct labor= $8,000
<u>Now, by difference, the direct materials:</u>
Direct material= Ending balance - allocated overhead - direct labor
Direct material= 20,000 - 6,400 - 8,000
Direct material= $5,600
Answer:
The budgeted materials needed in units for April = 67000 litres
Explanation:
The budgeted production for April = 68000 units
The budgeted production for may = 64000 units
The cost of raw material per unit = $1.70 per unit
It is given that at the end of each month the inventory should be = 25%
The April 1 inventory = 17000 units
Now calculate the material required for April production:![= [ Materials needed + ending inventory requirements - beginning inventory available ]](https://tex.z-dn.net/?f=%3D%20%5B%20Materials%20needed%20%2B%20ending%20inventory%20requirements%20-%20beginning%20inventory%20available%20%5D)
![= [ 68000 + (64000 × 25%) – 17000 ] = 67000 Litres](https://tex.z-dn.net/?f=%3D%20%5B%2068000%20%2B%20%2864000%20%C3%97%2025%25%29%20%E2%80%93%2017000%20%5D%20%3D%2067000%20Litres)
Therefore, the budgeted materials needed in units for April = 67000 litres