Answer:
Explanation:
Opening units 30000
Started 120000
150000
Closing 20000
Transffered 130000
Production Table W.Avg Method
A B C=A+B
Cost Element Complete Closing WIP Equivellant production
units
Material 130,000 20,000 (100%) 150,000
Coversion Cost 130,000 10,000 (50%) 140,000
Answer:
The correct answer is C.
Explanation:
Giving the following information:
Pinnacle Corp. budgeted $700,000 of overhead costs for the current year.
Pinnacle's plantwide allocation base, machine hours, was budgeted at 100,000 hours.
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 700,000/100,000= $7 per machine-hour.
Answer:
Different personal and cultural traits can explain why even though we know that planning our activities help a lot, we rarely do it.
Japanese society is extremely structured and they plan everything. There incredible economic success is the result of that. Once I was travelling on the same tour bus as a group of Japanese tourists, and their tour guide requested them to give him their schedules since being on vacations meant not following a plan. The tourists got all anxious and nervous because they were going to do something different, which was scary for them.
That day I started to question myself as to why I rarely plan things, and on the next days I really tried to do it, but I failed. One of the reasons I failed was that I was the only one planning what to do, no one else at work was. I felt like Cameron Diaz when she was making plans about where she should be planning on how to have fun. It was really boring, that is the reason why Japanese don't have children or even girlfriends, its easier to plan what to do with a doll.
There is something nice and good about being spontaneous, although sometimes I still feel that I need to plan a little more.
The statement that does not refer to the reason that aids in project crashing is
(D) there are no critical activities that can be crashed further.
Explanation:
Project crashing basically refers to the method by which the duration of the project is reduced .This can be done by
- Reducing the time taken by one or more critical activity
- By devoting more resources in order to complete the project as early as possible.
- The cost associated with the project is also increased
In Crashing,<u> the time is inversely related to the cost of the project</u>.It means that if the time of the project increase then the project cost is reduced and if the time o/duration of the project decrease then the cost involved in the project increases
Answer:
$21.65
Explanation:
The computation of the standard cost is shown below:
= Material cost + labor cost + factory overhead cost
where,
Material cost = 3 ÷ 4 × $5 per yard
= $3.75
Labor cost = 2 hours × $5.75 = $11.5
And, the factory overhead cost is
= $3.20 × 2 hours
= $6.4
So, the standard cost is
= $3.75 + $11.5 + $6.4
= $21.65