Answer:Gundy Enterprise journal $
Date
Jan 31 2021
Income statementl Dr 641.67
Mortage Interest. Cr. 641.67
Recognition of interest payable on mortgage loan for December 2021
Jan 31 2021
Mortgage principal Dr 635.52
Mortgage interest Dr. 641.67
Bank Cr. 1277.19
Narration.payment of principal and interest Interest due on mortgage loan as at January 31 2021.
Explanation:
The monthly installment payments of $1277.19 consist of both the principal sum and accompanying monthly interest.
The interest needs to be first recognized as an expenses into the income statement and increase in the mortgage loan. This will prevent an over deduction on the mortgage loan.
Choosing a location for a new business is one of the most important decisions entrepreneurs make during the planning phase of launching ventures. The location of a business can affect many aspects of how it operates, such as total sales and how costly it is to run.
Answer:
The correct answer is publish an advertisement on an internet job site
Explanation:
The job offer is the total amount of work offered by individuals in an economy.
The job offer must be based, fundamentally, on the remuneration obtained by it. Although there are also other factors that influence the supply of work, such as working conditions, the existence of extra-salary remuneration, the possibilities of promotion in employment and training at work, among others.
Answer:
The firm's cost of equity is C. 14.05 percent
Explanation:
Hi, we need to use the following formula in order to find the cost of equity of this firm.

Where:
r(e) = Cost of equity
rf = risk free rate
rm = Market rate of return
Everything should look like this.

So, this firm´s cost of equity is 14.05%
Best of luck
Answer:
Cost-plus-fixed-fee pricing
Explanation:
Cost-plus-fixed-fee pricing is when the contractor specifies the expenses of a project and a fixed fee for the services that provides which allows the contractor to earn a profit. In this type of pricing, the overall cost of the project is determined at the end and all the authorized costs are paid to the contractor in full. According to this, the answer is that these contractors use cost-plus-fixed-fee pricing to compensate them for any cost overruns.