Answer:
Minimize Z = 3x + 2y
Explanation:
Let x represent hamburger meal and let y represent hot dog meal. The objective is to minimize the total cost. The objective function will be
Z = 3x + 2y
The maximum capacity of restaurant is 200 meals while it has minimum cap for 100 meals.
Answer:
45
Explanation:
The formula to compute the number of parts is shown below:
= Demand × lead time × (1 + safety factor) ÷ kanban cards
= 300 units × 45 minutes × (1 + 20%) ÷ 6
= 300 × 0.75 hours × 1.2 ÷ 6
= 45
The 45 minutes would be 0.75 hours i.e 45 minutes ÷ 60 minutes = 0.75 hours.
So we consider all the components which are given in the question. Hence, all the information is relevant
Market condition is the correct answer.
Answer:
D. $1,344 unfavorable
Explanation:
We know,
Direct materials quantity variance = (Standard Quantity - Actual Quantity) × Standard price
Given,
Standard Quantity = 4,440 pounds of material
Actual Quantity = 4,650 pounds of material
Standard price = $6.40
Putting the values into the above formula, we can get,
Direct materials quantity variance = (4,440 - 4,650) pounds × $6.40
or, Direct materials quantity variance = -210 pounds × $6.40
Therefore, Direct materials quantity variance = $1,344
As the actual quantity is higher than standard quantity, the situation is unfavorable. Therefore, option D is the answer.