We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer:
The formula: e7 = (b7*d7)+(c7*d7*1.5)
Step-by-step explanation:
Given:
Hours worked = b7
Hourly rate = d7
Overtime hours = c7
Salary calculation = e7
Salary = Hours worked*hourly rate + (overtime*hourly rate)*1.5
Formula
e7 = (b7*d7)+(c7*d7*1.5)
The formula e7 = (b7*d7)+(c7*d7*1.5)
Hope this will helpful to you.
Thank you.
Answer: Chef Andre used more than 3 and one-half cups of flour.
Step-by-step explanation:
This is the > ‘greater than sign. For the question, we are to get the inequality that shows that"c is greater-than 3 and one-half".
Let Chef Andre be represented by c. Greater than is used to denote a situation when something is."more than" another thing. In this scenario,
Chef Andre used more than 3 and one-half cups of flour. This can be represented as C > 3 1/2.
This is the correct answer.