I believe you meant "why is the number of shifts multiplied by approximately 4.5 to obtain the total number of operators required to run the plant"
Answer and Explanation:
There are 3 shifts per day, 49 weeks per year and 5 shifts per operator per week
To get total number of operators required to run the plant, we multiply number of shifts in a year by number if operators per shift.
49 weeks×5 shifts= 245 shifts per operator per year
365×3 shifts= 1095 shifts per year
1095/245=4.5 operators per shift
total number of operators required to run the plant(per day) = 4.5×3= 13.5 approximately 14
total number of operators required to run the plant(per year) =4.5×1095=4927.5 approximately 4928
Answer:
Option A
Step-by-step explanation:
<u>Given equation is</u>
=> 3y = 6x + 3
<u>In slope-intercept form, it becomes</u>
=> 3y = 3(2x+1)
=> y = 2x+1
So, Slope = m = 2
<u><em>Parallel lines have equal slope, So any line parallel to the above line would have its slope equal to 2</em></u>
=> Line parallel to 3y = 6x + 3 is y = 2x + 10
The solutions for ‘x’ are 2 and -5
<u>Step-by-step explanation:</u>
Given equation:

Since the base on both sides as ‘12’ are the same, we can write it as



Often, the value of x is easiest to solve by
by factoring a square factor, setting each factor to zero, and then isolating each factor. Whereas sometimes the equation is too awkward or doesn't matter at all, or you just don't feel like factoring.
<u>The Quadratic Formula:</u> For
, the values of x which are the solutions of the equation are given by:

Where, a = 1, b = 3 and c = -10



So, the solutions for ‘x’ are


The solutions for ‘x’ are 2 and -5