Answer:
True
Explanation:
A project scope statement can be regarded as a statement that give out well detailed description as regards the the work which is needed to be done so that the output of a project can be delivered on agreed time period as well as within the allotted budget.
scope statement usually gives the outlines of the entire project as well as
any deliverables, it do entails list of stakeholders within the scope. The writting is usually done by project manager. It should be noted that Project scope statements must include the project boundaries, constraints, and assumptions.
Answer:
the after-tax cost of debt is: 27,090
Explanation:
assuming the entire among of the consulting services is tax deductible
we can determinate the after-tax cost as:
expense x (1 - tax rate) =
43,000 x (1 - 0.37) = <em>27,090</em>
<em />
<em>the rate of return of a potential investment is not relevant for this purpose as is paying right away and not giving time to invest in a project to pay the amount next year.</em>
Answer:
Which one of the following is most apt to align management's priorities with shareholders' interests?-Holding corporate and shareholder meetings at high-end resort-type locations preferred by managers-Compensating managers with shares of stock that must be held for a minimum of three years-Paying a special management bonus on every fifth year of employment-Increasing the number of paid holidays that long-term employees are entitled to receive peppe
Answer:
B)debit Interest Expense, $200; credit Interest Payable, $200
Explanation:
The adjusted journal entry for the interest expense is shown below:
Interest expense A/c Dr $200
To Interest payable $200
(Being the interest adjusted entry is recorded)
Since we have to record the interest expense from September 1 to September 30 which reflects 1 month and the computation of interest expense is shown below:
= Principal × rate × (number of month ÷ total number of months in a year)
= $40,000 × 6% × (1 ÷ 12)
= $200
Answer:
<u>Cost of common equity is 0.1333 or 13.3%</u>
Explanation:
P= D1/(r-g)
D1=3.00
g= 0.05
P=36
Here we have
,
3.00/(r-0.05) = 36
r-0.05= 3/36= 0.08333
r= 0.1333= 13.33%