The correct answer for this question is this one: "B. biologists and chemists." A new drug to combat acne has been developed from a compound that is found in a melon. The <span>scientists would contribute to the development of the drug are biologists and chemists.
</span>
Here are the choices:
A. <span>chemists only
B. biologists and chemists
C. biologists, chemists, and physicists
D. biologists, chemists, and physicians</span>
Answer:
It is called a WPS brutal force attack.
Explanation:
Wired and wireless networks are both susceptible to attacks. The wired network, the advantage as a cable connection, is more secure than wireless networks, but wireless network also have security measures like the wifi protected set up (WPS).
WPS is used to connect to a network without passphrase, but with a key combination or a PIN.
Brutal force attacks are used on WPS to forcefully generate the PIN, using a third party software.
Answer: i just learned something new.
Explanation:
Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
The essential technique for using CPM is to construct a model of the project that includes the following:
- A list of all activities required to complete the project (typically categorized within a work breakdown structure),
- The time (duration) that each activity will take to complete,
- The dependencies between the activities and,
- Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.
Answer:
The rules which could trigger at any period in time are referred to as the conflict set. A programming bug/conflict can occur when two programs compete for the same resource such as memory or register etc.
A Conflict Resolution Strategy is is a protocol which highlights which decision will be triggered first.
The best way to resolve conflict is to first determine the kind of conflict it is. Hardware conflicts can be resolved by first troubleshooting the hardware and in some instances unplugging the hardware causing the conflict.
When hardware creates conflicts it may be due to a driver issue. reverting to an old driver or updating the existing one may solve the problem.
Software conflicts can be resolved by installing updates or complete uninstallation.
Cheers!