10

On May 1, 2016, Varga Tech Services signed a $6,000 consulting contract with Shaffer Holdings. The contract requires Varga to pr

ovide computer technology support services whenever requested over the period from May 1, 2016, to April 30, 2017, with Shaffer paying the entire $6,000 on May 1, 2016.
How much revenue should Varga recognize in 2016? (Do not round intermediate calculation.)
Business
1 answer:
saw5 [17]3 years ago
4 0

Answer:

Varga should recognize $4,000 as revenue in 2016.

Explanation:

As the cash received in advance is recorded as unearned revenue which is a liability for the Varga Tech Services because they did not provide the services yet. On  December 31,  Eight months have passed and services for these month has been provided. So the revenue of 8 month months of 2016 will be recognized and recorded at year end.

Serive Contract = $6,000 for 12 months

Revenue Recognized in 2016 = $6,000 x 8/12 = $4,000

You might be interested in
Ahngram Corp. has 1,000 carton of oranges that cost $20 per carton in direct costs and $19.00 per carton in indirect costs and s
andrew11 [14]

Answer:

The incremental income from processing the oranges into orange juice would be =$51000.

Explanation:

Incremental income from further process= (Selling price per unit- Additional cost per unit)*No. of units sold

= ($66 per unit-$15 per unit)*1000 units

= $51000

6 0
3 years ago
The production possibilities curve below shows the hypothetical relationship between the production of guns (national defense) a
balu736 [363]

Answer:

Marginal opportunity cost is the number of units of good 1 that are sacrificed for producing an additional unit of other good.

A) If we increase the production of butter from 1 to 2 then Guns production decreases from 36 to 26. Thus opportunity cost of second unit of butter is 10 guns.

B) Total opportunity cost of 2nd unit of butter = 18 guns

C) marginal opportunity cost of producing the third unit of butter = 12 Guns

D) Total opportunity cost of third unit of butter = 30 Guns

3 0
3 years ago
Bell Company, a manufacturer of audio systems, started its production in October 2017. For the preceding 3 years, Bell had been
LekaFEV [45]

Answer:

variable cost per unit 150 dollars

Explanation:

As we aren't provided with a volume. We calculate considering variable costying system which onyl count variable cost as cost of goods manufactured:

raw material                            $    75 per unit

labor 5 hours x 14 per hour = $    70 per unit

variable ovehread                   $     5 per unit

Variable cost per unit              $  150 per unit

the fixed overhead cost

5,110 + 3,730 + 1,550 + 6,600 + 8,760 = 25,750

will be considered cost of the period under variable costing

8 0
2 years ago
Consider the following two projects. Both have costs of $5,000 in Year 1. Project 1 provides benefits of $2,000 in each of the f
frutty [35]

Answer:

1. Compute the net benefits using a discount rate of 6 percent.

Net befit of Project 1 = $629.04

Net befit of Project 2 = $1,578.47

2. Repeat using a discount rate of 12 percent.

Net befit of Project 1 = $339.38

Net befit of Project 2 = - $373.39

3. What can you conclude from this exercise?

(a) Project 2 should be chosen when the discount rate is 6 percent.

(b) Project 1 should be chosen when the discount rate is 12 percent.

Explanation:

Note: See the attached excel file for the calculations of net benefits for Project 1 and Project 2.

3. What can you conclude from this exercise?

(a) When a discount rate of 6 percent is used, both Project 1 and Project 2 have positive net benefit. But the net benefit of Project 2 of $1,578.47 is higher than the net benefit of Project 1 of $629.04.

Therefore, project 2 should be chosen when the discount rate is 6 percent.

(a) When a discount rate of 12 percent is used, only Project 1 has a net benefit of $339.38, but the net benefit of Project 2 is negative at minus $373.39.

Therefore, project 1 should be chosen when the discount rate is 12 percent.

Download xlsx
6 0
3 years ago
Real Angus Steakhouse purchased land for $75,000 cash. They also incurred commissions of $4,500, property taxes of $5,000, and t
Stella [2.4K]

Answer:

c. $84,300.

Explanation:

The computation of the total cost of the land is shown below:

= Purchase cost of land + commission incurred + property taxes + title insurance

= $75,000 + $4,500 + $4,000 + $800

= $84,300

We simply added that costs which are related to the land i.e purchase cost, commission , property taxes ,and title insurance. The $1,000 cost should not be considered.

4 0
3 years ago
Other questions:
  • Gross Investment $18
    9·1 answer
  • Jolly Candies is a U.S.-based company that manufactures and distributes candy bars and snack foods globally. The company sources
    8·1 answer
  • We argued that when the economic growth in the US is greater than the (economic) growth rates of our trading partners, the trade
    14·1 answer
  • Opportunity cost refers to _________.a. current economic conditions. b. your personal values.c. trade-offs when a decision is ma
    12·1 answer
  • Stock and bond markets:
    5·1 answer
  • The largest component of GDP by far is A. net exports. B. personal consumption expenditures. C. government purchases of goods an
    7·1 answer
  • Which industry is the source of essential raw materials?
    11·2 answers
  • On December 31, 2017, Ainsworth, Inc., had 720 million shares of common stock outstanding. Thirty one million shares of 7%, $100
    12·1 answer
  • Jmes Graham Manufacturing is a small manufacturer that uses machine-hours as its
    8·1 answer
  • If, when you consume another piece of candy, your marginal utility is zero, then?
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!