Answer:
2.92 Rounded to the 100th
Step-by-step explanation:
Swap x and y's positions
f(x) is another way of saying y, so basically tha initial function is y = 1-2x^3.
Change it up to x = 1-2y^3 and solve for y
X - 1 = - 2y^3
(X - 1)/-2 = y^3
So the cube root of ((x-1)/2) = y
Answer:
y=x-1
Step-by-step explanation:
Solution: Estimated time for the work is 40 hour work week.
Estimated payment to 3 laborers working 40 hours at cost $14 per hour is:
$1680
Estimated payment to 6 masons working 40 hours at cost $24 per hour is:
$5760
Estimated cost of material = $3143
Contractor wishes to make a profit of $500
Therefore, the mathematical expression that will give the estimated cost of the job is:

The estimated total cost is:
Cost =$11083