Answer:
b. Feedforward control
Explanation:
Feedforward control is a form of proactive control that includes measures that pertain to prevent certain consequences and safety hazards. This company wants to prevent their employees form getting injured from particles during manufacturing. So, this is an example of feedforward control, that aims to prevent, not react.
Answer: you have to pay back the loan once you start making money. in general you have to pay back the loan. everyone wants free money.
Answer: redesign its products to eliminate those features that might have market appeal, but would excessively increase production costs.
Explanation:
The main aim of every organization are typically cost minimization and profit maximization. If I wanted to advise a company on the kind of actions to take to perform value chain activities more cost effectively, I'll tell them to improve their supply chain efficiency as well as use economies of scale and effective utilization of its resources.
Therefore, redesigning its products to eliminate those features that might have market appeal, but would excessively increase production costs is wrong as this will only lead to increase in cost.
The answer is true. Individuals who need to work for themselves frequently like to work their business, at any rate at first, as a sole proprietorship. Leeway of the sole proprietorship is that it is a generally simple and cheap type of business to set up. One disadvantage of a sole proprietorship is that the proprietor has boundless obligation. Notwithstanding, right now, Eric isn't stressed over hazard. The boundless risk factor does not seem, by all accounts, to be an issue for him.
Answer:
c. $5.1 per hour.
Explanation:
Estimated Manufacturing overhead = $249,000
Estimated direct labour hours = 50,000
Predetermined overhead Rate = Estimated Manufacturing overhead / Estimate direct labor hours
Predetermined overhead Rate = $249,000 / 50,000
Predetermined overhead Rate = $4.98
The given is inconsistent with the options given in this question. A similar question is attached with this answer. The following answer is made according to the attached question. please find that.
Estimated Manufacturing overhead = $254,000
Estimated direct labour hours = 50,000
Predetermined overhead Rate = Estimated Manufacturing overhead / Estimate direct labor hours
Predetermined overhead Rate = $254,000 / 50,000
Predetermined overhead Rate = $5.08 = $5.1 per hour