Octavia should tell the customer that she doesn’t know the answer right now, but she will try to figure it out as soon as possible, and it may take a few days.
Another great option is for Octavia to ask a coworker right away who may know the answer to the question.
The calculated profit per unit for base-case, worst-case is, and best-case for the management of Brinkley corporation is:
<h3>The Profit per unit for base-case:</h3>
45 - 1 1- 24 - 3 = $7
<h3>Profit per unit for worst case:</h3>
45 - 12 - 25 - 3 = $3 per unit
<h3>Profit per unit for best case:</h3>
45 - 10 - 20 - 3 = 12$ per unit
b. The mean profit per unit is given as $7.05
c. The reason the simulation approach is preferable is due to the fact that it can help to determine the probability of profit as a particular amount, unlike the what-if scenario analysis.
It can also create different scenarios for possible resources.
d. The probability of the fact that the profit per unit woul be less than 5 is 9%
Read more on risk analysis here: brainly.com/question/6955504
Answer:
so they can end up spending less on interest payments and credit card fees.
Explanation:
Answer:
Project A
Years Cashflows Discount factor Present values
0 250,000 1 -250,000
1-10 45,100 6.144 277,094.40
Sum of all present value=NPV=27,094.40
IRR (by using trial and error method) = 12.4696%
Note: Discount factor for the year 1-10 is calculated by using annuity formula i.e [1-(1+10%)]/10% = 6.144
Project B
Years Cashflows Discount factor Present values
0 (350,000) 1 (350,000)
1 72,500 0.91 65,975
2 65,500 0.83 54,365
3 73,800 0.75 55,350
4 71,500 0.68 48,620
5 69,800 0.62 43,276
6 75,500 0.56 42,280
7 31,000 0.51 15,810
8 47,500 0.47 22,325
9 55,500 0.42 23,310
10 29,200 0.38 11,096
Sum of all present values=NPV=32,407
IRR(by using trial and error method=12.4186%
On the basis of NPV project B is better because it gives higher NPV than project A. Whereas, Project A is better than project B on the basis of IRR because project A has slightly higher IRR than project B.
b)The conflict between both the investment appraisal technique is likely due to different cash flow patterns of both the project. In such situation decision should be based on NPV because this is an absolute measure