It will take 5 days for Montegro Flooring Company to complete this job
<u>Solution:</u>
Given, The Montegro Flooring Company can replace 200 square feet of carpet with tile in one day
They accept a job replacing carpet with tile in an apartment that measures 977.5 square feet
We have to find how many days will it take the Montegro Flooring Company to complete this job?
Now, according to given information,
200 square feet ⇒ 1 day
Then, 977.5 square feet ⇒ n days
Now, by chris cross method

Hence, the company requires 5 days approximately.
There are 4 roses in each arrangement
Answer:
easy A
Step-by-step explanation:
Answer:120
Step-by-step explanation:
Volume of box=length x width x height
Volume of box=4x2.5x1.5
Volume of box=15
Cube length=1/2=0.5
Volume of cube=0.5x0.5x0.5
Volume of cube=0.125
Number of cube that can be packed inside the box=15 ➗ 0.125=120