Answer:
Answer is the FCAC is greater than the TBC.
Refer below.
Explanation:
A second method for determining the forecasted cost at completion assumes that, regardless of the efficiency rate the project or work package has experienced in the past, the work to be performed on the remaining portion of the project or work package will be done according to budget. If the cumulative actual cost is greater than the cumulative earned value, then: FCAC is greater than the TBC.
Answer:
Selling price= $336.6
Explanation:
Giving the following information:
Variable costs:
direct materials= $122
direct labor= $52
variable overhead= $67
Total unitary variable cost= $241
Total fixed costs= 679,000 + 114,000= $793,000
<u>First, we need to calculate the total unitary cost:</u>
Total unitary cost= (793,000/12,200) + 241
Total unitary cost= $306
<u>Now, the selling price:</u>
Selling price= 306*1.1
Selling price= $336.6
Answer:
Option (C) is correct.
Explanation:
The goods with a perfectly inelastic demand with any changes in the prices of the commodities are generally have no effect on the demand for a good. This means that if there is an imposition of tax on the good with a perfectly inelastic demand then this will lead to increase the price level by the full amount and therefore, the incidence of this tax is fully borne by the consumers.