Answer:
Total allocation= $318.25
Explanation:
Giving the following information:
Loading and unloading: Number of pieces - $85,785 - 90,300
Travel: Miles driven - $468,000 - 585,000
Logistics: Hours - $65,520 - 3,120
Determine the overhead allocated to Job XZ3275 which has 150 pieces, requires 200 miles of driving, and 0.75 hours of logistics.
First, we need to calculate the estimated overhead rate for each activity:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Loading and unloading= 85,785/90,300= $0.95 per piece
Travel= 468,000/585,000= $0.8 per mile
Logistics= 65,520/3,120= $21 per hour
Finally, we can allocate overhead to Job XZ3275:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Loading and unloading= 0.95*150= $142.5
Travel= 0.8*200= $160
Logistics= 21*0.75= $15.75
Total allocation= $318.25