Answer:
Safety Stock is 336.62 units
Explanation:
As per given data
Demand = D = 50,000
Ordering Cost = S = $35
Holding Cost = H = $1 per unit per year
Weekly Demand = Demand / 50 weeks = 50,000 / 50 = 1,000 units per week
Weekly Demand during Lead time of 3 weeks = 1000 x 3 = 3,000 units
Standard Deviation = 216.51 units
Desired Service level = 94%
The Z score at 94% service level is 1.55477
Safety Stock = Zscore x standard deviation = 1.55477 x 216.51
Safety Stock = 336.62
Answer:
Should shut down if its short-run average variable cost exceeds $25.
Explanation:
This directly explains the firms profit maximizing level of output in a short run. And in the scenario above, the firm made a $25 gain per unit output, it is advised the firm should shut down if its shut run average variable cost exceeds $25.
A process that companies undergo to determine the best output and price levels in order to maximize its return. The company will usually adjust influential factors such as production costs, sale prices, and output levels as a way of reaching its profit goal. There are two main profit maximization methods used, and they are Marginal Cost marginal Revenue Method and Total Cost total Revenue Method. Profit maximization is a good thing for a company, but can be a bad thing for consumers if the company starts to use cheaper products or decides to raise prices.
False that just don’t make since lol