Answer:
I need info
Step-by-step explanation:
1st question
$23,760-(4000+6000)=$13,760
$13,760 x 4%=$ 550.40
2nd question
$43,300-(2000+2000)= $39,300
$39,300 x 5%= $1,965
Answer:
50
Step-by-step explanation:
code in parm so the angle o is equal to e
that is a property of the parm
Answer:
(7.5 , 5.5)
Step-by-step explanation:
The midpoint is halfway between the two end points:
Its x value is halfway between the two x values
Its y value is halfway between the two y values
To calculate it:
Add both "x" coordinates, divide by 2
Add both "y" coordinates, divide by 2
Answer:
•A c-chart is the appropriate control chart
• c' = 8.5
• Control limits, CL = 8.5
Lower control limits, LCL = 0
Upper control limits, UCL = 17.25
Step-by-step explanation:
A c chart is a quality control chart used for the number of flaws per unit.
Given:
Past inspection data:
Number of units= 100
Total flaws = 850
We now have:
c' = 850/100
= 8.5
Where CL = c' = 8.5
For control limits, we have:
CL = c'
UCL = c' + 3√c'
LCL = c' - 3√c'
The CL stands for the normal control limit, while the UCL and LCL are the upper and lower control limits respectively
Calculating the various control limits we have:
CL = c'
CL = 8.5
UCL = 8.5 + 3√8.5
= 17.25
LCL = 8.5 - 3√8.5
= -0.25
A negative LCL tend to be 0. Therefore,
LCL = 0