Answer:
From the information given about the contract and its execution between the two parties involved( That is, Parc and Glaze), the option 2 is most likely.
2. Glaze will win because Glaze substantially performed and Parc prevented complete performance.
Explanation:
It is stated that Glaze was hired to remodel and furnish an office suite, after a submitted plans by Glaze were approved by Parc. It was further stated that the construction and painting had been done.
Although, with Glaze purchasing minor accessories which Parc rejected because they did not conform to the plans is a breach of contract, but that can be corrected by calling Glaze to order. However, it was Parc that refused to allow Glaze to make necessary corretion and complete the project and also refused to pay Glaze any part of the contract price.
Answer:
Gavin's delivery cycle time=11.6 days
Explanation:
The delivery cycle time is the time between when an order from a customer is received and the time the product is actually delivered to the customer. It can be calculated using the formula below;
DCT=W+I+P+M+Q
where;
DCT=delivery cycle time
W=wait time=5 days
I=inspection time=0.7 days
P=process time=2.5 days
M=move time=0.4 days
Q=queue time=3 days
In our case;
DCT=unknown
W=5 days
I=0.7 days
P=2.5 days
M=0.4 days
Q=3 days
replacing;
DCT=5+0.7+2.5+0.4+3=11.6 days
Gavin's delivery cycle time=11.6 days
Answer:
Other things equal, the fall in the price of plastic would shift Pic's marginal cost curve to the right. To maximize profits, Pic should increase its output. Since other firms in the industry do not enjoy the reduction in marginal costs, the market supply curve would not change and the market price of toothpicks would remain unchanged. Pic Industries would enjoy higher profits in the short-run
Answer:
B. the winning potential of the sports team using the stadium
Explanation: