Answer:
a. A Pareto Chart is a graph that shows the frequency of flaws and their overall impact.
b. For instance, by using Pareto Charts, you might discover that putting in 13% of the effort yields 87% of the results. Alternatively, 30% of underlying causes might be addressed to solve 70% of problems.
c. Pareto charts are important for deciding which defects or negative risks should be prioritized in order to achieve the best overall results.
Explanation:
a. Explain the concept of a Pereto Chart
A Pareto Chart is a graph that shows the frequency of flaws and their overall impact. A Pareto chart is a fundamental quality tool that can be used to identify the most common problems, complaints, or any other countable and categorizeable factor. A Pareto chart is a form of graph that includes both bars and a line graph, with bars representing individual values in descending order and a line representing the cumulative total.
b. Provide an example
The Pareto Principle explains how there is frequently a lack of symmetry between the labor you do and the outcomes you get. For instance, by using Pareto Charts, you might discover that putting in 13% of the effort yields 87% of the results. Alternatively, 30% of underlying causes might be addressed to solve 70% of problems.
b. Explain how the concept of the Pereto Chart might be used in making decisioins about handling negative risks which could impact a project or organization.
A Pareto diagram is used to distinguish between the important and inconsequential components of a problem. It frequently shows the most common sources of defects, the most common type of fault, the most common grounds for customer complaints, and so on in quality control.
Therefore, Pereto Chart might be used in making decisioins about handling negative risks which could impact a project or organization as it allows a project team or an organisation to know where to focus their improvement efforts by graphically distinguishing the parts of an issue. Pareto charts are therefore important for deciding which defects or negative risks should be prioritized in order to achieve the best overall results.